02/26/2020
Inspection, Routine
|
01b - Critical |
Water Quality: Water Testing Equipment |
Inspector Comments: Numerous Taylor pool chemical reagents in the pool test kits were expired. Corrected on site.
|
09a - Non-Critical |
Deck Areas: Deck Areas |
Inspector Comments: The pool and spa skimmers were not equipped with skimmers. The spa had one skimmer.
|
10a - Non-Critical |
Chemicals: Storage and Handling of Chemicals |
Inspector Comments: Muriatic acid bottles were stored next to containers of sodium bicarbonate in the pool pump room. The pool chemicals were stored next to the furnace.
|
11a - Non-Critical |
Mechanical Room: Recirculation System, Piping, and Maindrains |
Inspector Comments: The operator did not have a schematic of the piping system available for reference. The pool circulation pipes were not marked with directional flow arrows. The spa yellow suction line had a directional arrow that was oriented backwards. The pool and spa flow meters were installed near pipe elbows, they were not installed equidistant from the pipe elbows.
|
14c - Non-Critical |
Records and Certifications: Chemical Records Maintained |
Inspector Comments: Pool and spa chemical records were not available for review during the inspection.
|
01/23/2019
Inspection, Routine
|
01a - Critical |
Water Quality: Chemical Quality; Disinfection and pH |
Inspector Comments: The spa free available chlorine was 0.0 ppm. The spa pH was 6.8.
|
01b - Critical |
Water Quality: Water Testing Equipment |
Inspector Comments: One container of Taylor R-0870 DPD powder expired on 06/2018. Corrected on site.
|
08a - Non-Critical |
Water Quality; Other: Water Quality; Other |
Inspector Comments: The spa total alkalinity was 30 ppm. The spa calcium hardness was 675 ppm. The spa saturation index was -0.6.
|
09a - Non-Critical |
Deck Areas: Deck Areas |
Inspector Comments: The spa had one skimmer, rather than two. Weir gates with float valves were not installed in the pool and spa skimmers.
|
09b - Non-Critical |
Deck Areas: Steps, Ladders, Diving |
Inspector Comments: The pool and spa stairs did not have two-inch color contrasting edges.
|
10a - Non-Critical |
Chemicals: Storage and Handling of Chemicals |
Inspector Comments: Containers of basic hardness and muriatic acid were stored next to each other in the pump room.
|
11a - Non-Critical |
Mechanical Room: Recirculation System, Piping, and Maindrains |
Inspector Comments: There was no schematic diagram of the pool and spa circulation piping available for reference.
|
11e - Non-Critical |
Mechanical Room: Make-Up Water and Cross Connections |
Inspector Comments: Make up water lines for the pool and spa were not protected by an air gap or a reduced pressure assembly backflow preventer.
|
14c - Non-Critical |
Records and Certifications: Chemical Records Maintained |
Inspector Comments: The spa pH and chlorine were not checked every two hours.
|
02/13/2018
Inspection, Routine
|
01a - Critical |
Water Quality: Chemical Quality; Disinfection and pH |
Inspector Comments: There was no detectable free chlorine in the swimming pool water.
|
02b - Critical |
Disinfection: Automatic and Continuous Disinfection, Approved |
Inspector Comments: The automatic chlorinator servicing the swimming pool did not provide at least 0.4 ppm of free chlorine to the water.
|
08a - Non-Critical |
Water Quality; Other: Water Quality; Other |
Inspector Comments: The spa water had 1.6 ppm of combined chlorine. The spa water had 12 ppm of free chlorine. The pool had 50 ppm of total alkalinity and the spa had 60 ppm of total alkalinity. The spa calcium hardness was 690. The spa water temperature was 106 degrees F.
|
09a - Non-Critical |
Deck Areas: Deck Areas |
Inspector Comments: A weir gate was not installed in the spa skimmer. The spa had only one skimmer.
|
09b - Non-Critical |
Deck Areas: Steps, Ladders, Diving |
Inspector Comments: The pool stairs were not provided with two-inch non-slip treading.
|
10a - Non-Critical |
Chemicals: Storage and Handling of Chemicals |
Inspector Comments: Numerous pool chemical containers were stored within a few feet of the pool and spa heaters.
|
11a - Non-Critical |
Mechanical Room: Recirculation System, Piping, and Maindrains |
Inspector Comments: The pool piping system was not labeled with directional arrows.
|
11e - Non-Critical |
Mechanical Room: Make-Up Water and Cross Connections |
Inspector Comments: The pool and spa makeup water was not protected by an air gap or a reduced pressure assembly.
|
14c - Non-Critical |
Records and Certifications: Chemical Records Maintained |
Inspector Comments: The pool and spa free chlorine and pH levels were recorded once per day, and the calcium hardness and flow meter readings were not recorded at all for the month of February, 2018. Chemical check readings were not recorded for February 12, 2018.
|
14d - Non-Critical |
Records and Certifications: CPO or Approved Certification |
Inspector Comments: The establishment did not have a Certified Pool Operator on staff.
|
03/27/2017
Inspection, Routine
|
08a - Non-Critical |
Water Quality; Other: Water Quality; Other |
Inspector Comments: The spa water temperature was 105 degrees F. The spa total alkalinity was 60 ppm.
|
09a - Non-Critical |
Deck Areas: Deck Areas |
Inspector Comments: The spa had one skimmer. The pool and spa skimmers did not have floating wier gates.
|
10a - Non-Critical |
Chemicals: Storage and Handling of Chemicals |
Inspector Comments: Liquid clarifier bottles were stored directly above an uncovered pail of calcium hydrochloride tablets.
|
14c - Non-Critical |
Records and Certifications: Chemical Records Maintained |
Inspector Comments: The pool and spa chemical levels were not recorded since March 21st. Chlorine and pH were recorded once per day from March 1st to 21st. The pool and spa flow meter readings were not recorded at all in the month of March, 2017.
|
05/04/2016
Inspection, Routine
|
01a - Critical |
Water Quality: Chemical Quality; Disinfection and pH |
Inspector Comments: The spa chlorine was less than 0.4 ppm.
|
08a - Non-Critical |
Water Quality; Other: Water Quality; Other |
Inspector Comments: The pool and spa total alkalinity were both 50 ppm. The pool and spa calcium hardness were both above 600 ppm. The pool water was 70°F, and the spa water was 105°F.
|
09a - Non-Critical |
Deck Areas: Deck Areas |
Inspector Comments: The spa did not have five feet of unobstructed deck on all sides.
|
10a - Non-Critical |
Chemicals: Storage and Handling of Chemicals |
Inspector Comments: Liquid water clarifier containers were stored directly above containers of calcium hypochlorite tablets in the chemical storage locker.
|
11a - Non-Critical |
Mechanical Room: Recirculation System, Piping, and Maindrains |
Inspector Comments: The pump room did not have a schematic drawing of the piping system posted.
|
14c - Non-Critical |
Records and Certifications: Chemical Records Maintained |
Inspector Comments: Chlorine and pH were not recorded three times per day as required, they were recorded once per day.
|
06/08/2015
Inspection, Routine
|
316 - Minor |
Color coded pipes & arrows; guages & flow meter installed; schematic diagram posted, instructions |
Inspector Comments: No schematic diagram was posted in the pump room.
|
32 - Minor |
Minimum 5ft unobstructed, cleanable, slope, non-slip, drain |
Inspector Comments: The table in the corner of the pool room blocked the 5 foot clearance around the pool.
|
474 - Major |
Chemical parameters ( Free Chlorine and/or pH) must be within required range; immediate closure |
Inspector Comments: The free available chlorine in the spa was 0.2 ppm.
|
475 - Minor |
Pool chemical parameters must be within required range |
Inspector Comments: The combined chlorine in the spa was 1.3 ppm.
|
49 - Minor |
CPO or equivalent; water quality records available; tested at proper frequency; turnover |
Inspector Comments: Pool records were not recorded for any days in June 2015.
|
06/26/2014
Inspection, Routine
|
416e - Major |
Disinfection provided, maintained, proper handling of chemicals:Liquid chemicals by dry chemicals |
Inspector Comments: Liquid chemicals were stored above dry chemicals in the chemical closet.
|
475 - Minor |
Pool chemical parameters must be within required range |
Inspector Comments: The temperature of the spa was greater than 104°F.
|
49 - Minor |
CPO or equivalent; water quality records available; tested at proper frequency; turnover |
Inspector Comments: A CPO certificate was not provided.
|
01/30/2014
Inspection, Routine
|
316 - Minor |
Color coded pipes & arrows; guages & flow meter installed; schematic diagram posted, instructions |
Inspector Comments: The facility does not have a schematic diagram posted for the pool or spa.
|
474 - Major |
Chemical parameters ( Free Chlorine and/or pH) must be within required range; immediate closure |
Inspector Comments: The pH for the pool and spa was below the required 7.2 – 8.0 the pH for the pool was at 7.1, the pH for the spa was at 6.8.
|
475 - Minor |
Pool chemical parameters must be within required range |
Inspector Comments: The total alkalinity for the pool 50 spa 40, the required range is 70-180. The water temperature for the spa was at 107.4°F, the maximum temperature is 104°F.
|
49 - Minor |
CPO or equivalent; water quality records available; tested at proper frequency; turnover |
Inspector Comments: The facility does not have a CPO on staff or under contract for the pool or spa. The chemical records were only recorded once per day, not required amount of 3 times per day.
|